We are excited for the first round of Measure H bond projects to start over the summer of 2026! Progress on construction timelines will be shared throughout the summer for our school community.
Updated Aug 6, 2026
(Left) New flooring in a Life Oak Elementary classroom.
(Right) New overhead lights and wiring in the Green Acres admin building.
(Left) New flooring in a Green Acres classroom. Baseboards have not yet been installed.
(Right) The Del Mar perimeter fencing project is nearly complete.
Del Mar Elementary School
Perimeter Fencing Project
Completed!
Replacement of Existing Two Broken Gates
Completed!
Restriping of Drop-Off Lane
In the design & review process.
Cypress Tree Abatement (Removal of Dead & Dying Trees)
Completed!
Furniture Refresh (Phase I): New Student Chairs TK-2 and New Teacher Chairs
All furniture has been delivered!
Note: The number of projects this year has been limited due to the summer programming held on the Del Mar campus.
Green Acres Elementary School
New Classroom, Library and Office Flooring
Completed!
Major Roofing Replacements on All Buildings
Construction is almost complete and the contractor is working on the finishing touches and cleanup.
Resealing & Restriping of Large Blacktop Area
Construction is anticipated to be complete by the end of July.
Replacement of Asphalt Adjacent to Primary Playground/Solar Panels
Completed!
Furniture Refresh (Phase I): New Student Chairs TK-2 and New Teacher Chairs
All furniture has been delivered!
HVAC Replacement: Preschool Portable
Completed!
Main Domestic Water Backflow Replacement
Delayed
New Overhead Lighting and Wiring Repair in Admin Building
Completed!
Live Oak Elementary School
New Classroom, Library and Office Flooring
Completed!
Major Roofing & Gutter Replacements on All Buildings
Construction is almost complete and the contractor is working on the finishing touches and cleanup.
New TK/K Playground
This project is on-track to be completed in the Fall of 2026. The order has been placed with the manufacturer for the playground.
Primary Playground Corkeen Play Surfacing
This project is on-track to be completed in the Fall of 2026.
WiFi Infrastructure Upgrade for Room 19
Completed!
Furniture Refresh (Phase I): New Student Chairs TK-2 and New Teacher Chairs
All furniture has been delivered!
Shoreline Middle School
(Phase I) Modernization of Main Gymnasium and the "Little Gym"
Construction has started on the stage and bleacher removal. This project is on-track to be completed in the Fall/Winter of 2026.
Hallway Wall Refresh
Delayed! Materials & scheduling issue.
Shark Gate
Gate is installed; however, the district is still working on the final marine-themed artwork.
Major Window Repairs
Delayed! The district is still searching for a contractor who can take on this specialized project.
Furniture Refresh (Phase I): New Student Chairs for Grades 6-8 and New Teacher Chairs
All furniture has been delivered!
Ocean Alternative Education Center
Perimeter Fencing Project
Completed!
Furniture Refresh (Phase I): New Student Chairs and New Teacher Chairs
All furniture has been delivered!
District Buildings
Maintenance Yard
New Pavement, Seal and Stripe Project
In progress!
New Central Kitchen Project
Architectural & Engineering Design and Review
In progress!